Gallatin SRL Landfill Project Image
GALLATIN SOUTH RAIL LOOP LANDFILL
ENVIRONMENTAL

To clean up the Gallatin Fossil Plant and provide space for future coal combustion residual hauling and ash disposal, Barnard is working with the Tennessee Valley Authority to construct a new landfill.

As part of an effort to clean the Tennessee Valley Authority Gallatin’s Fossil Plant located in Sumner County, Tennessee, Barnard is constructing a new landfill to provide space for future coal combustion residual (CCR) hauling and final disposal of ash. The project includes the construction of Cells 4 and 5, which span across 32.2 acres and 34.9 acres of lined landfill, respectively. Additionally, Barnard is constructing new sediment basins and a contaminated stormwater basin, which require 235,000 CY of rock excavation and over 1.5 million CY of earthworks. Other work includes the construction of HDPE piping systems (17,500 LF of leachate pipe and 5,400 LF of contaminated stormwater pipe), installation of 25,800 LF of 25kV cable, excavation work by blasting, development, and maintenance of an onsite borrow, site electrical works, demolition of an existing conference center, and perimeter haul road construction.

OVERVIEW

Location: Sumner County, Tennessee

Owner: Tennessee Valley Authority (TVA)

Engineer: AECOM

Contract type: Fixed Lump Sum, Fixed Unit Price

Status: Currently Under Construction

HIGHLIGHTS

  • 682,400 CY of structural fill
  • 575,570 CY of geologic buffer
  • 218,210 CY of clay liner
  • 232,350 CY of protective cover
  • 3,123 LF of construction drain pipe
  • 2-ea. leachate tanks with 1-million gallon capacity
  • 3 million SF of 60-Mil HDPE liner
  • 3,214,000 SF of geocomposite
  • 2,525,000 SF of rain cover
  • 232,500 SF of Fabri-Form installation
  • 6,450 LF of underground duct bank
  • Four new electrical power pads

67.1 ACRES OF LINED LANDFILL

682,400 CY OF STRUCTURAL FILL

6,450 LF OF UNDERGROUND DUCT BANK

Gallatin SRL Footer