Project Header_ Barren Ridge
BARREN RIDGE RENEWABLE TRANSMISSION PROJECT
POWER DELIVERY

The 62-mile Barren Ridge Renewable Transmission Project traversed desert terrain and ascended rugged mountains within Angeles National Forest lands, requiring robust environmental planning to protect fragile ecosystems along the route.

In September 2016, Barnard completed the construction of a new 230kV transmission line for LADWP, connecting the Barren Ridge Switching Station with the new Haskell Canyon Switching Station. This EPC project—one facet of LADWP’s plan to increase production and use of renewable energy—featured an aggressive schedule. Barnard and design engineer Black & Veatch initiated design prior to Notice of Award to efficiently complete the preconstruction services, which involved design of the towers, lines, and foundations; full-scale tower testing; and procurement of all required permanent materials, including 16 million pounds of lattice steel, 2.1 million feet of conductor, 500,000 feet of OPGW, and all necessary line hardware.

In addition to the challenges presented by the terrain, the entire project alignment fell within or near existing utility corridors, and stakeholder and landowner relations were critical to project success. The Barnard team sequenced the tri-circuit outage work strategically, scheduled as many activities as possible during non-outage periods, and re-sequenced around areas of delayed permitting or land acquisition. Each of LADWP’s pre-set outages was completed successfully, and the transmission line was energized one month ahead of schedule.


OVERVIEW

Location: Lancaster, California

Owner: Los Angeles Department of Water and Power (LADWP)

Engineer: Black & Veatch

Contract Type: Engineer, Procure, Construct (EPC)

Status: Completed

HIGHLIGHTS

  • 2017 ENR California Excellence in Safety Best Project & Best Project in Energy/Industrial, Southern California
  • 2016 NUCA Top Job, Electric Power
  • Design of 10 tower types
  • 62 miles of new 230kV double- and triple-circuit transmission line
  • 60 miles of groundwire and OPGW
  • 12,500 CY of concrete
  • 1,233 drilled concrete pier foundations
  • 48 miles of improved access road
  • 12 miles of new access road
  • Intense environmental monitoring and compliance

62 miles of new 230kV transmission line constructed

2.1 million ft. (395 miles) of 2312 Thrasher ACSS/AW conductor installed

306 lattice tower structures designed, fabricated, assembled, and installed

Project Footer _ Barren Ridge