Project header_West of Devers
WEST OF DEVERS UPGRADE PROJECT
POWER DELIVERY

The West of Devers Upgrade Project serves as a critical component in SCE’s effort to meet California’s renewable power goals.

For this EPC project, Barnard removed and replaced 184 circuit miles of existing 220kV transmission lines with new double-circuit 220kV transmission lines, though this was anything but a typical linear utility project. Over a three-year construction period, Barnard worked through 16 separate outages coordinated with the California Independent System Operator. The outage sequence required three of four existing circuits in the right-of-way to remain energized at all times so SCE could maintain service to its customers.

The project concluded under budget and ahead of schedule, despite the challenging outage sequence and the COVID-19 pandemic. In fact, SCE energized the line more than five months ahead of schedule, an achievement the team attributes to partnering and the “project-first” mentality it promoted. The upgrade has tripled electricity transmission capacity from 1,600 MW to 4,800 MW and enables SCE to bring additional renewable and battery energy storage resources to the grid.

OVERVIEW

Location: Redlands, California

Owner: Southern California Edison (SCE)

Engineer: Black & Veatch

Contract Type: Engineer, Procure, Construct (EPC)

Status: Completed

HIGHLIGHTS

  • 2022 Marvin M. Black Partnering Excellence Award Winner
  • 2022 Construction Risk Partners Build America Award Winner
  • 184 circuit miles of new 220kV transmission line
  • Tower and pole design, fabrication, assembly and installation
  • Procurement and installation of 1590 kcmil Lapwing conductor
  • Removal of 602 existing transmission structures
  • Removal of 184 circuit miles of existing conductor
  • Upgrades to 66kV sub-transmission and 12kV distribution lines
  • Management of environmental monitoring and compliance scopes
  • Earthwork and grading to support construction

5.9 million feet conductor

386 double-circuit steel lattice towers

83 double-circuit tubular steel poles

Project footer_West of Devers