A rockslide in a remote coastal region of British Columbia damaged penstock essential to providing water to Alterra Power Corp.’s hydroelectric facility. The company, through the Toba Montrose General Partnership, required a contractor that could move quickly during the region’s short construction season to stabilize the mountainside and replace the damaged penstock.

Barnard Construction of Canada Ltd. responded on a fast-track schedule to remove and replace approximately 1,100 LF of 96-inch-diameter steel penstock that was damaged in the naturally occurring rockslide. This repair project included rock removal, slope stabilization and drilling and blasting in addition to the penstock construction. The project took place in the remote Sunshine Coast region of British Columbia where the logistics of material and equipment delivery were solely by ocean delivery. The project also required establishment of a temporary remote camp for living quarters.

Montrose Penstock Repair

Hydropower Business Development

Kevin Schneider
p: 406.586.1995 x222
e: kevin.schneider@barnard-inc.com

Gavin Tasker
p: (406) 586-1995 x324
e: gavin.tasker@barnard-inc.com

Del Shannon, P.E.
p: (406) 586-1995 x347
e: del.shannon@barnard-inc.com

world

Company Headquarters
BARNARD
701 Gold Avenue
Bozeman, MT
59715

p: 406-586-1995 / f: 406-586-3530
Email BARNARD

BARNARD Careers

We're looking for bright, innovative, hard-working people - those who thrive on demanding and challenging tasks and who bring out the best in others on their Team. Our people are eager for responsibility.

down_arrow View Available Positions

Explore BARNARD