Dawson Creek Sanitary Sewer Project
Project Type:
Pipelines & Utilities
Location: Hillsboro, Oregon
Owner: Unified Sewerage Agency
Engineer: David Evans and Associates
Contract Value: $7.3 million
Contract Type: Negotiated


Project Photos
*Click on thumbnail to enlarge

Project Highlights
  • Installed 10,542 LF of double barrel 36-inch and 42-inch HDPE gravity flow sanitary sewer
  • Alignment within the stream corridor
  • 50-foot-wide right-of-way
  • 16-foot-wide Uni-mat system running the length of the wetlands
  • Constant wetlands mitigation and restoration
  • Environmental permitting, monitoring and compliance
  • Numerous crossings
  • Tunneling / boring
  • Sheet piling

Project Details

The Dawson Creek Sanitary Sewer Project presented Barnard with environmental, restricted access, and tight schedule challenges. Working within a 50-foot right-of-way and utilizing a 13-foot-wide trench box, Barnard crews installed nearly two miles of double barrel 42-inch and 36-inch sewer line. Adding to the complexity of the project was the work required through wetlands. Barnard used a 16-foot wide Uni-mat system running the length of the wetlands to protect the natural environment. Barnard’s involvement in the design and permitting process contributed to the successful completion of this difficult project.

Project Location

"Barnard Construction did an excellent job throughout all phases of the project. They were extremely responsive to the owner's needs and issues."

-
Richard Attansito, P.E., Senior Associate, David Evans and Associates, Inc.